Dulles Rail back on track, managers say

Published



The first phase of the Dulles Rail project, which was six months behind schedule last August, is now just 11 days late and on target to be completed next year, officials said. That’s because managers and contractors were able to accelerate work on some parts of the $2.8 billion project, said Pat Nowakowski, the project manager.