NRC still seeking why spot at NC nuke plant missed

Published



HOLLY SPRINGS, N.C. (AP) — An outside contractor hired to look for flaws in a Duke Energy nuclear reactor near Raleigh last year missed a quarter-inch spot of corrosion and cracking near the reactor core that forced a full shutdown last month after new eyes reviewing year-old data found the problem, federal regulators said Thursday.

Four smaller spots were fixed during a refueling last year, but the flaw that forced the May 15 shutdown at the Shearon Harris nuclear plant wasn’t found until new contractors reviewed ultrasonic tests from last year, Nuclear Regulatory Commission inspectors said during a public meeting.