JACKSON, Miss. (AP) — The Southern Co. says it may cost another $40 million to finish the $5 billion-plus power plant and mine it’s building in eastern Mississippi’s Kemper County.
The Atlanta-based parent of Mississippi Power Co. said Tuesday that it would set aside money in the plant’s budget to cover possible start-up problems. Critics have warned the technology, which turns soft lignite coal into a gas, extracts chemicals and burns the gas to generate electricity, may not work as designed. A coal gasification plant built by Duke Energy in Edwardsport, Ind., using different technology, struggled during its startup phase.