DHS cuts contract for significantly delayed cutter, saving $260 million

Published June 5, 2025 9:00am ET



The Department of Homeland Security announced on Wednesday that it cancelled the ongoing but delayed production of a legend-class National Security Cutter, saving more than $260 million.

Shipbuilding company Huntington Ingalls Industries (HII) began production on the cutter in May 2021 and it was scheduled to be delivered to the Coast Guard by November 2024 at the latest. In August 2024, however, HII informed the service that the earliest possible delivery would be spring 2029 after a series of delays and setbacks.

Already a print subscriber? Click here to login/register your account